Subsequent to the Phase I preliminary wind energy feasibility and siting study EBEC contracted again with ASA to perform a Phase II study with the scope of performing a detailed feasibility study of developing a project at the Tiverton site. The detailed study, presented herein, evaluated the project size and layout options, siting considerations, procurement and development considerations, ownership structures, financing opportunities, and legislation considerations. The results are presented as four different options for EBEC to act as owner, developer and operator, evaluating the associated development cost and potential revenue streams as well as a third party developer owned and operated project and the associated assumed project description and revenue stream.
Recommended Citation
Applied Science Associates, Inc., "EBEC Phase II Wind Energy Project Feasibility Study: ASA Project 10-060, Final Report" (2010). East Bay Energy Consortium Documents. 29.